Hon Steve Martin asks about the status, location, staffing, and work undertaken/planned by the Westport Roads Integrated Project Team (IPT). The Minister provides a consolidated answer detailing the IPT's establishment, location, staffing levels, and current/future projects.

AnsweredQoN 276Legislative Council
Asked
5 May 2026
Portfolio
Transport

QuestionView source ↗

Westport Roads Integrated Project Team
276. Hon Steve Martin to
the parliamentary secretary representing the Minister
for Transport:
I refer to the
development of Westport.
(1) Has the Westport roads integrated project
team been fully established and, if not, what is its status?
(2) In what building or buildings are the
offices of the IPT based?
(3) How many persons are employed as part
of the IPT in FTE terms?
(4) In relation to (3), are these persons
counted in the Westport office FTE headcount?
(5) What work has the IPT undertaken to
date and what work is the IPT expected to undertake over the next 12 months?

AnswerView source ↗

I thank the
honourable member for some notice of the question and provide the following
answer on behalf of the Minister for Transport.
(1)–(5) The
integrated project team has been established in the Perth CBD with between 30
and 35 FTE. The team is responsible for project definition and development
for the Kwinana Freeway upgrade project and the Anketell Road upgrade project.