Mrs Warr asks about the Geraldton Health Campus redevelopment's completion date, original schedule, budget, and reasons for budget variations. The response indicates the project is on track and within budget.

✅ AnsweredQoN 1769Legislative Assembly
Asked
18 February 2026
Answered
18 March 2026
Response Time
9 days
Portfolio: Health Infrastructure

Question

I refer to the Geraldton Health Campus redevelopment, and I ask:(a) What is the estimated completion date for the redevelopment;(b) What was the original date the project was scheduled to be finished;(c) What is the current estimated budget for the project; and(d) What reasons are attributed to any variations in the budget?

Answer

The Geraldton Health Campus Redevelopment Project is the biggest redevelopment of the facility since the early 2000s under the previous Gallop Labor Government. (a-b) The project remains on track for completion this year, which aligns with the original date for project completion following the award of the Managing Contract. (c-d) The budget remains at $190.2 million, as per the 2025-26 State Budget papers.

Explore WA Government Data

Search the full archive in the free dashboard, or query programmatically via API.

Explore more