This parliamentary question from Hon Dr Steve Thomas probes Synergy's modelling of additional peak gas generation capacity to support Western Australia's energy transition, specifically asking about a 300 MW business case and other potential capacities. It also seeks information on the retirement dates and capacities of state-owned gas-fired generators.

AnsweredQoN 391Legislative Council
Asked
13 May 2026
Portfolio
Energy and Decarbonisation

QuestionView source ↗

Synergy—Peak gas generation
391. Hon Dr Steve Thomas to the Leader of the House representing the Minister for Energy
and Decarbonisation:
I refer to the need
for additional peak gas generation to underpin the state's energy transition.
(1) Has Synergy been asked to model a
business case for 300 megawatts of additional peak gas generation capacity
through either the construction of generation or the provision of power purchase
agreements?
(2) Is Synergy modelling a business case
for any other additional peak gas generation and, if so, how much?
(3) Which state-owned gas-fired
generators have age-based retirement dates prior to 2035, and what is the
capacity of those generators?

AnswerView source ↗

I thank the
honourable member for some notice of the question.
(1)–(2) Synergy models a variety of electricity generation
and demand scenarios.
(3) They are all Pinjar frame 6
units with nameplate capacity of approximately 228 megawatts and one
Pinjar frame 9 unit with nameplate capacity of approximately 111 megawatts.